Denny Regrade, Seattle, Washington
From Wikipedia, the free encyclopedia
Contents |
[edit] Neighborhood
The Denny Regrade is a neighborhood in Seattle, Washington, that stretches north of the central business district to the grounds of Seattle Center. Its generally flat terrain was originally a steep hill, taken down as part of a mammoth construction project in the first decades of the 20th century. The neighborhood is named after that project.
[edit] Regrading project
The Denny Regrade project was the removal of Denny Hill, one of the proverbial seven hills of Seattle. It ran east from First Avenue between Pike Street and Denny Way. Hill and street were named after the Denny family, who were among the city's earliest white inhabitants. The First Avenue regrade was started in 1897 and completed on January 6, 1899. From 1902 to 1911, the hill was sluiced into Elliott Bay by pumping water from Lake Union using hydraulic mining techniques. In 1929, the final pieces of the hill were removed using steam shovels.
[edit] Denny Hill
Seattle is located on a narrow strip of land between Lake Washington on the east and Puget Sound on the west. The north-south orientation of the lake and of the city's many hills is the result of glaciation. The terrain was first gouged by south-moving glaciers, and when they retreated, marked by mounds of rock debris left in their wake. Denny and Queen Anne Hills are two of those north of what is now downtown Seattle.
[edit] Photographs
Early 20th century postcards showing the Denny Regrade.
[edit] See also
Eugene McAllaster, Denny Regrade consulting engineer
[edit] External links
- Seattle Daily Journal of Commerce online article: Top Projects of the Century in Washington State: #7, Denny Regrade
- Biography of Eugene L. McAllaster, 1866-1946, Denny Regrade consulting engineer